Bridge replacement project to begin on K-156 in Finney County

The Kansas Department of Transportation, traffic changes that will affect travel on K-156.
Beginning Monday, April 14, there will be a bridge replacement project approximately 3 miles west of the west K-23/K-156 junction in Finney County.
During construction, a shoo-fly detour will redirect traffic around the bridge construction. Reduced speed limits will be posted for the construction of the new bridge. Motorists should expect minimal delays at different times, and a width restriction of 12 feet will be in effect throughout the project.
L & M Contractors Inc., of Great Bend, is the contractor on this $2.4 million project that is expected to be completed by the beginning of December, weather permitting.
For more information, contact Craig Schlott P.E., District Assistant Construction and Materials Engineer, at (620) 765-7096, or Yazmin Moreno, KDOT Southwest Public Affairs Manager, at (620) 765-7080.
The map below shows the approximate location of the location of project in blue.